(last revised January 11 2001)
CONTACTS (at ING and PN.S respectively):
Technical: Romano Corradi (rcorradi@ing.iac.es) Nigel Douglas (ndouglas@astro.rug.nl)
Organisation: Rene Rutten (rgmr@ing.iac.es) Koen Kuijken (kuijken@astro.rug.nl)
| ITEM | SUMMARY | COMMENTS A DATE INDICATES A MESSAGE, SEE "Correspondence" FOR DESCRIPTION | ||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| JSC | KK notified JSC | |||||||||||||||||||||||||
| PATT | PN.S to apply for science time via NL and UK PATT around Sep 12 2000, for September deadline | WHT proposal w01an011 provisionally awarded 2 Dark nights from the NL PATT one from UK PATT, April 16, 17, 18 | ||||||||||||||||||||||||
| flange | required, awaiting quote from Kevin Dee (last questions from Paul Jolley 31.8.00) | is contracted to MSO | ||||||||||||||||||||||||
| A.G. box (1) | check that PN.S doesn't interfere with aquisition and guiding | OK PROVIDED that the instrument does not protrude into the hole of the lowermost ring of the AGB box (RC 6.10.00) - John Hart confirms sighting this | ||||||||||||||||||||||||
| A.G. box (2) | check that CuNe, CuAr and white light fully illuminate the 12' square field | Confirmation received that illumination is "pretty uniform" over a 16cm box (which is 12') at Cass (RC 18.12.00) | ||||||||||||||||||||||||
| control | Instrument requires a cable connection
to link a 19" rack (Cass) with a PC (Control room). Standard at the WHT
is The PN.S has several cabling possibilities. In early discussions we requested a Centronics type link (see sketch) and two 19" rack spaces but we are now working on a simplified arrangement.
Confirmation received that a suitable 19" crate is available and can
be mounted (RC 15.12.00); exact orientation is not known so agree with John Hart
on cable length of 5m between motors and 19" crate. | ND is in contact with John Mills (ejm@ing.iac.es) about the use of the PAT105 connectors. Confirmation received that a PC is available for us, but contact Phil Symonds (pgs@ing.iac.es) close to arrival. data | via ING acquisition system |
| safety | email from Alan Chopping (23.10.00, akc@ing.iac.es)
-- there are not specific regulations: suggests
that "if you have a primary
plan/design for the instrument we should meet and discuss the safety
implications with all interested parties such as electronics and
mechanical" |
| handling | awaiting specific reply about handler, but
ING will provide ... technical assistance
for mounting and dismounting the instrument | 12.6.00
| detectors and cryostat mechanical interface
| two (2k x 2k x 15um) CCDs required,
PN.S is designed to accomodate
ING standard dewars | Detector info: La Palma engineering
| Drawings of the adaptor flanges attachment (RC 6.10.00) have now been looked at by John Hart storage | in WHT dome area until further notice;
dry nitrogen fill required |
| transportation
|
|
On Tue, 24 Apr 2001, John Hart wrote:
"Rick in the mail room confirmed that the only way TNT could get it over
there would be by economy air at $6 per item, $9.50 per kilo and would take
about a week"
| instrument readiness
|
mostly at RSAA
|
see status
| commissioning
|
Aaron, Koen, Mike, Nigel 12-19 July 2001
| see the commissioning
checklist
| |