PN Spectrograph: Maintenance and Operations PN Spectrograph: WPD60.html


Work Package Description: Maintenance and Operations
Version: 10 June 2003 (provisional)
Performed by: all
Followed by: MT
Team participants: none

Inputs Required:
PNS operating, H-alpha arm in construction

Tasks Included:
60.01 upgrade of control unit

Work Package Outputs:
- 19" rack with serial interface and 4 motors

Tasks Explicitly Excluded:

Agreed Completion Date:

tbd

Budget Allocation:

      3500 preliminary electronics work 
       933 PASP page charges OAC 

Signed:

Name:

Date: