PN.S PROJECT PAGE:

PROJECT LINKS


PHASE B PROJECT DEFINITION

This area, based on the Phase B study conducted at RSAA (WPD10) is intended to be a full set of specifications for the PN Spectrograph. It includes links to the files containing the optical and mechanical plans. It includes the results of the Phase B study into stray light and vignetting. It also contains quotes for all the external optics, and when these quotes are revised they will be placed in this area. The Phase B report was initially done on the basis of 1200 g/mm gratings but a revised report was prepared in October 1999. Included in the WORD file:

Other parts of the Phase B study:

Current best quotes for PN.S optics:
  OIII Filters   Barr Associates   $US 11,700  
  Halpha Filters   Barr Associates   $US 12,500  
  Calibration Lamps       not required at WHT
  Dichroic   RSAA + Rofin   $A 8,000  

Phase B final report as submitted by Gabe Bloxham (RSAA) 12/11/1999 (word file)


WORK PACKAGE DESCRIPTIONS

The individual tasks have been collected into work packages and primary responsibility for each of these has been assigned to one of the participating institutes


WPD fileDatePackage Description Performed by:Followed by:Cost ($Ak)
WPD0024 July 1998Project ManagementProject OfficePI 0.0
WPD051 January 1999Phase A StudyKIND 18.3
WPD1010 November 1998Phase B StudyRSAA KCF 45.2
WPD203 January 2000Phase C Optics: mainRSAA, INAOEKT 89.9
WPD2113 January 2000Phase C Optics: otherRichardson Lab, BARRMA, ND 92.1
WPD256 January 2000Phase C Mechanical: mainRSAAKCF, ND 40.0
WPD2611 December 2000Phase C Mechanical: supplementaryNFRAKK, ND 49.6
WPD2822 December 1999Phase C ElectricalRSAA (probably)KCF, MA 3.5
WPD303 December 2000Phase C IntegrationRSAAND, KT 17.8
WPD353 January 2000Phase D Mechanical: flangestbdKK, MA 1.9
WPD4024 July 1998Phase A/D Assembly and Test, CommissioningKI/OACKK, MA 0.5
WPD5031 January 2000H alpha armtbdtbd 155.9
WPD6010 June 2003Maintenance and OperationsallMT 4.4

OUTSTANDING TASKS

Date is highlighted if the task is urgent


TaskDescriptionAction by: Required by:Status & Comments
21.08commission design of second grating unitNDtbd for one-arm operation if required  
21.09order auxiliary gratingNDtbdfor one-arm operation if required  
21.10manufacture auxiliary gratingNDtbdprobably standard grating  
28.04specify and order lampsMAtbdpower supply required! long delivery time?  
30.02provision of test star or other alignment and calibration devices as requiredRSAADec 2000  
30.10possible stray light problem near CCD windowRSAAJune 2001  
50.03Dichroic substratetbdtbdquote has expired  
50.04Dichroic coating (front and rear)tbdtbdmore design work required, check polarization effects  
50.05Halpha camera opticstbdtbddesign available, stray light analysis required  
50.06Halpha AR coatingtbdtbdquote has expired  
50.07Halpha filtertbdtbd  
50.08R-band filter filtertbdtbd  
50.09Filter wheel/flippertbdtbd  
50.10Third CCD cameratbdtbdif needed  
50.11Halpha arm: assembly and test on PN.Stbdtbd  
60.01upgrade of control unit asap  

TIMELINE

09-05-1997 Kick-off meeting at OAC
19-06-1997 Progress meeting at ESO
08-10-1997 Kick-off for Dutch participation
18-05-1998 Progress meeting in Groningen (MA, ND, KK, KT, de Haas, Schoenmaker)
30-07-1998 Design Review at MSO
24-09-1998 Final Optical Design
01-03-1999 MOU signed (except for ASTRON and ESO)
26-03-1999 Order placed (INOAE) for camera optics
26-03-1999 Order placed (RSAA) for collimator optics
19-07-1999 Phase B Design Review in Leiden
22-07-1999 Final Drawings of Collimator
10-11-1999 WPD10 Phase B study complete
01-12-1999 Phase C mechanical construction, RSAA bid accepted in principle
10-12-1999 Camera optics arrive AAO
03-05-2000 Collimator optics complete
26-05-2000 All optics delivered to CSIRO for testing
xx-05-2000 Gratings ordered at Richardson Grating Lab
31-05-2000 Phase C mechanical construction, RSAA part complete
19-07-2000 Phase C mechanical construction, ASTRON part shipped
09-08-2000 ASTRON hardware arrives at RSAA
04-09-2000 CSIRO report on optics received
07-09-2000 Richardson gratings arrive at AAO
21-09-2000 Gratings examined at RSAA
22-09-2000 All optics sent to RSAA (from CSIRO)
30-09-2000 WHT 01A semester observing proposal submitted
26-10-2000 2nd pass filter specs/quotation
27-10-2000 Mask design complete
xx-11-2000 Re-lap and polish scratched collimator lens, re-machine collimator housings and re-make lens spacer, re-work camera sleeves, lens spacers
08-01-2001 Order for coatings (28 surfaces) placed with ROFIN (fax NGD)
12-01-2001 5 Collimator lenses sent from RSAA to ROFIN
05-02-2001 ROFIN completes coating of first 9 lenses
08-02-2001 CSIRO refunds cost of testing work
23-02-2001 Bloxham completes re-polishing of camera optics
28-02-2001 Last of the lenses sent from RSAA to ROFIN
02-03-2001 April commissioning postponed (email NGD to RGMR)
16-03-2001 Coated lenses received at RSAA, oil on grating reported
30-04-2001 New spacers made for rear elements in cameras
01-05-2001 Grating cleaned
04-05-2001 Cameras and collimator assembled
14-05-2001 Filter #1 arrives at RSAA (from Barr via Keith)
22-05-2001 PN.S assembled, incl filter in cell ????
04-06-2001 D Jones in RSAA for additional check, baffle required
14-06-2001 PN.S shipped from RSAA
22-06-2001 PN.S shipped from Australia to Frankfurt
30-06-2001 PN.S flown from Frankfurt to Las Palmas
03-07-2001 PN.S shipped from Las Palmas
10-07-2001 PN.S clears customs and transported to ING
13-07-2001 PN.S team arrives at ING
16-07-2001 Successful commissioning at the WHT